Road Construction on Elk Vale Road and New Underwood Road - 7/29/19

Road construction on Elk Vale Road and New Underwood Road will begin on Monday, July 29, 2019. Please expect traffic delays.

  • Elk Vale Road Project: 4” Asphalt Surfacing from the County line, North to the Intersection of Elk Creek Road

  • New Underwood Road Project: Dig-outs, Base Course and Asphalt Surface Treatment from 0.4 Miles South of the intersection of Elk Creek Road, North to SD Highway 34

Highway Department - Project Updates

Completed Work

Section Graveling

  • Indian Creek Road - 3,000 Ton

  • Stoneville Road - 1,500 Ton

  • Avalanche Road - 2,500 Ton

Bridge Repair

  • Sulfur Creek Bridge on Stoneville Road - Now Open

Culvert Repair

  • Brustel Road - Now Open

Working Week of June 17

Section Graveling

  • Stoneville Road

Culvert Repair

  • New Underwood Road

  • Elk Creek Road